| << Go Back
|
| Control # |
2101920 |
Region/TIP |
D2 20-00 |
Local ID |
|
Total Cost |
$137,557 |
| Lead Agency |
Transit / Rail Division |
Contact |
Rail Bureau |
District |
2 |
County |
Eddy |
| Project Type |
Rail/Highway Crossing (22) |
Air Quality |
|
TCM |
|
Construction |
2019 Start |
| Title |
GRAND AVE RR CROSSING #019974R, ARTESIA |
| Limits |
GRAND AVENUE from Milepost 3 to Milepost 3.1 (.1 mile) |
| Description |
DESIGN AND CONSTRUCT NEW CROSSING SURFACE AND APPROACHES FOR 4 TRACKS |
| Production Date |
|
Letting Date |
|
|
|
|
|
| Phase |
Fund Source
|
Prior FFY |
FFY2020 |
FFY2021 |
FFY2022 |
FFY2023 |
Future FFY |
Total |
| CON |
ROAD FUND (RF) |
$5,433 |
-
|
-
|
-
|
-
|
-
|
$5,433 |
| CON |
ROAD FUND (RF) (AC) |
$8,324 |
-
|
-
|
-
|
-
|
-
|
$8,324 |
| CON |
ROAD FUND (RF) (ACCP) |
- |
$8,324
|
-
|
-
|
-
|
-
|
$8,324 |
| CON |
ROAD FUND (RF) (ACCP OFFSET) |
- |
$-8,324
|
-
|
-
|
-
|
-
|
$-8,324 |
| CON |
RR CROSSING - HAZ ELIMINATION (RRS) |
$48,893 |
-
|
-
|
-
|
-
|
-
|
$48,893 |
| CON |
RR CROSSING - HAZ ELIMINATION (RRS) (AC) |
$74,907 |
-
|
-
|
-
|
-
|
-
|
$74,907 |
| CON |
RR CROSSING - HAZ ELIMINATION (RRS) (ACCP) |
- |
$74,907
|
-
|
-
|
-
|
-
|
$74,907 |
| CON |
RR CROSSING - HAZ ELIMINATION (RRS) (ACCP OFFSET) |
- |
$-74,907
|
-
|
-
|
-
|
-
|
$-74,907 |
| Total Construction |
$137,557 |
- |
- |
- |
- |
- |
$137,557 |
| Total Programmed |
$137,557 |
-
|
-
|
-
|
-
|
-
|
$137,557 |
| Total Programmed (incl. ACCP) |
$54,326 |
$83,231 |
- |
- |
- |
- |
$137,557 |
|
Map Coming Soon
Map location not available
|
| << Go Back
|
| VERSION |
FFY |
SOURCE |
CON |
TOTAL |
| 8 |
20-00 2020 STIP Year 2020-2025 - Pending FHWA Approval |
2019 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$48,893 |
$48,893 |
| 8 |
20-00 2020 STIP Year 2020-2025 - Pending FHWA Approval |
2019 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$74,907 |
$74,907 |
| 8 |
20-00 2020 STIP Year 2020-2025 - Pending FHWA Approval |
2019 |
ROAD FUND (RF) |
$5,433 |
$5,433 |
| 8 |
20-00 2020 STIP Year 2020-2025 - Pending FHWA Approval |
2019 |
ROAD FUND (RF) |
$8,324 |
$8,324 |
| 8 |
20-00 2020 STIP Year 2020-2025 - Pending FHWA Approval |
2020 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$74,907 |
$0 |
| 8 |
20-00 2020 STIP Year 2020-2025 - Pending FHWA Approval |
2020 |
ROAD FUND (RF) |
$8,324 |
$0 |
|
TOTAL FOR VERSION 8 |
$137,557 |
$137,557 |
|
| 7 |
18-22.1 2018 Sept. 2019 Admin Mods 1 - closed |
2019 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$104,106 |
$104,106 |
| 7 |
18-22.1 2018 Sept. 2019 Admin Mods 1 - closed |
2019 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$48,893 |
$48,893 |
| 7 |
18-22.1 2018 Sept. 2019 Admin Mods 1 - closed |
2019 |
ROAD FUND (RF) |
$5,433 |
$5,433 |
| 7 |
18-22.1 2018 Sept. 2019 Admin Mods 1 - closed |
2019 |
ROAD FUND (RF) |
$11,568 |
$11,568 |
| 7 |
18-22.1 2018 Sept. 2019 Admin Mods 1 - closed |
2020 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$104,106 |
$0 |
| 7 |
18-22.1 2018 Sept. 2019 Admin Mods 1 - closed |
2020 |
ROAD FUND (RF) |
$11,568 |
$0 |
|
TOTAL FOR VERSION 7 |
$170,000 |
$170,000 |
|
| 6 |
18-07 2018 Amendment 7 - Pending Federal Approval |
2019 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$104,106 |
$104,106 |
| 6 |
18-07 2018 Amendment 7 - Pending Federal Approval |
2019 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$48,893 |
$48,893 |
| 6 |
18-07 2018 Amendment 7 - Pending Federal Approval |
2019 |
ROAD FUND (RF) |
$5,433 |
$5,433 |
| 6 |
18-07 2018 Amendment 7 - Pending Federal Approval |
2020 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$104,106 |
$0 |
| 6 |
18-07 2018 Amendment 7 - Pending Federal Approval |
2020 |
ROAD FUND (RF) |
$11,568 |
$11,568 |
|
TOTAL FOR VERSION 6 |
$170,000 |
$170,000 |
|
| 5 |
18-03 2018 Formal Amendment |
2022 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$300,337 |
$300,337 |
| 5 |
18-03 2018 Formal Amendment |
2022 |
* STATE (SM) |
$33,371 |
$33,371 |
|
TOTAL FOR VERSION 5 |
$333,708 |
$333,708 |
|
| 4 |
18-01 2018 |
2022 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$300,337 |
$334,537 |
| 4 |
18-01 2018 |
2022 |
* STATE (SM) |
$33,371 |
$33,371 |
| 4 |
18-01 2018 |
2022 |
* STATE (SM) |
$0 |
$3,800 |
|
TOTAL FOR VERSION 4 |
$333,708 |
$371,708 |
|
| 3 |
18-00 2018 20182023-WRK-0 |
2022 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$288,000 |
$322,200 |
| 3 |
18-00 2018 20182023-WRK-0 |
2022 |
* STATE (SM) |
$32,000 |
$32,000 |
| 3 |
18-00 2018 20182023-WRK-0 |
2022 |
* STATE (SM) |
$0 |
$3,800 |
|
TOTAL FOR VERSION 3 |
$320,000 |
$358,000 |
|
| 2 |
16-09 2016 20162021-WRK-9 |
2020 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$288,000 |
$322,200 |
| 2 |
16-09 2016 20162021-WRK-9 |
2020 |
* STATE (SM) |
$0 |
$3,800 |
| 2 |
16-09 2016 20162021-WRK-9 |
2020 |
* STATE (SM) |
$32,000 |
$32,000 |
|
TOTAL FOR VERSION 2 |
$320,000 |
$358,000 |
|
| 1 |
16-08 2016 20162021-WRK-8 |
2020 |
RR CROSSING - HAZ ELIMINATION (RRS) |
$288,000 |
$322,200 |
| 1 |
16-08 2016 20162021-WRK-8 |
2020 |
* STATE (SM) |
$32,000 |
$32,000 |
| 1 |
16-08 2016 20162021-WRK-8 |
2020 |
* STATE (SM) |
$0 |
$3,800 |
|
TOTAL FOR VERSION 1 |
$320,000 |
$358,000 |
|
|
|
| << Go Back
|
| VERSION |
|
PUBLIC DESCRIPTION |
STATUS |
APPROVAL DATE |
| 8 |
20-00 2020 TIP |
GRAND AVE RR CROSSING #019974R, ARTESIA |
PROGRAMMED |
9/19/2019 |
| 7 |
18-22.1 2018 ADMIN |
GRAND AVE RR CROSSING #019974R, ARTESIA |
PROGRAMMED |
N/A |
| 6 |
18-07 2018 FORMAL |
GRAND AVE RR CROSSING #019974R, ARTESIA |
PROGRAMMED |
07/10/2019 |
| 5 |
18-03 2018 FORMAL |
GRAND AVE RR CROSSING #019974R, ARTESIA |
PROGRAMMED |
7/2/2018 |
| 4 |
18-01 2018 ADMIN |
GRAND AVE RR CROSSING #019974R, ARTESIA |
PROGRAMMED |
N/A |
| 3 |
18-00 2018 TIP |
DRAFT: GRAND AVE RR CROSSING #019974R, ARTESIA |
PROGRAMMED |
09/29/2017 |
| 2 |
16-09 2016 FORMAL |
DRAFT: GRAND AVE RR CROSSING #019974R, ARTESIA |
PROGRAMMED |
09/29/2017 |
| 1 |
16-08 2016 FORMAL |
DRAFT: EAST GRAND AVENUE AT CROSSING #019974R |
PROGRAMMED |
09/29/2017 |
|
|
|
|